This post was last edited by liaifeng on 2018-9-10 at 18:17. How long does it take for a 1.8 million-ton methanol-to-olefins project to go from construction to completion?
It’s hard to say how long it will take to complete construction and start operations two years after the funds are available; if the funds are not available, it’s even more difficult to determine. For Fude Energy, the production of olefins from 1.8 million tons of methanol is expected to be feasible in about two years. There are also several companies whose production started four or five years ago.
For domestic refineries, the process takes about a year: as soon as the project is approved, large-scale bidding begins, with the selection of equipment also starting at that time. No cost can be spared; for example, the delivery time for compressors and reactors is several months. In the initial phase, construction work must be carried out around the clock, and in the later stages, a large number of welders are needed to work in shifts for the installation of steel structures and equipment. Without enough workers, all the money spent will be wasted. There must also be people who have actually worked on projects and truly understand them. If you don’t lack funds and have a good project manager, you can ensure both safety and quality while still completing the construction quickly. The project manager is the key figure; their main responsibilities are coordination and technical oversight. Those who do the actual work can be assisted by newer employees, but they still need to have mentors to guide them, as there are still many things they need to figure out on their own
Thank you. Two years or more is considered a normal timeframe for progress; barring issues such as policy or funding problems, the current situation is that it usually takes three years or more
Thank you; good decision-makers are better than anything else
I’ve been using it here for over 4 years, and it’s indeed affected by many factors
The construction timelines of Baotou and China Coal Yulin can be used as a reference, as these two projects are representative.
I heard that the Ningxia Baofeng 600,000-ton olefin project has the lowest investment cost and the fastest construction time.
If the quality were also the best, that wouldn’t be normal! Hehe