Let’s discuss the punch list and how to best understand it.
Foreign companies are all referred to as the unreasonable list, right?
Punch list, items not completed. Option A: Rectification is mandatory ; Option B: There is room for negotiation, or the conditions for completion are not yet met ; Option C, in simple terms, means they don’t like you; they want you to change. If you don’t change, it doesn’t matter – it’s not essential.
This post was last edited by raylikenoother on 2016-11-30 at 10:37. List of remaining items, unfinished lists, or list of items requiring correction
A PUNCH LIST is a detailed list of corrective actions for the issues identified during the trial operation of a facility as part of a project’s commissioning process. Under normal circumstances, this rectification is carried out during a shutdown that occurs after the system has been operating for a certain period of time. Not only must the equipment be repaired, but the deviations during the trial operation also need to be analyzed and fine-tuned from a process perspective. Personal opinion
According to Wikipedia: A punch list is a document prepared toward the end of a construction project that lists tasks that do not meet the contract specifications and must be completed by the contractor before final payment is issued. These tasks may include incomplete or incorrect installations, or accidental damage to existing finishes, materials, and structures. A punch list is a document outlining tasks that fail to comply with contractual requirements at the end of a construction project; the contractor must complete these tasks before receiving the final payment. This may include incomplete or incorrect installation, or completed installations with damaged materials or structures. As for translation, I still think that a \"list of remaining items,\" a \"list of unfinished tasks,\" or a \"list of items requiring correction\" would be more appropriate. I’ve worked on some projects, but I’ve never seen a punchlist after the system has been shut down for a while; please @renyongchang explain this in detail, as what you described sounds more like something related to trouble-shooting or performance evaluation.
This layout has been turned off. I’m not sure if the reply will be seen. I have been involved in Phase 3 projects, and there are many minor installation defects or issues that are not detected during the installation phase; they can only be identified through water testing and commissioning. Therefore, the punch list should be prepared within one or two weeks after the project’s commissioning, and then work should be carried out to make the necessary corrections based on that list. Of course, if any major safety hazards are identified during testing, the vehicle must be stopped immediately for rectification. @raylikenoother
The tail item list is primarily used for pressure testing design. Regarding the definition of Item A, it refers to those items that must be modified before pressure testing, mainly those related to welding
The tail terms are classified as follows: Category A affects the functionality and security; Category B impacts aesthetics; Category C has little impact and time constraints are not strict; Category D is intended to be resolved through negotiation