Piping work is complete; how should the excess amount for material accounting be determined?

2016-12-13View Original

Thread Content

For example, if the length of a DN20 pipe is 45 meters, how much material needs to be ordered in reality?
Reply #22016-12-13
The designed quantity is what it is; the procurement quantity is determined jointly by the material control department and the purchasing team, based on the procurement ratios derived from previous projects of similar scale
Reply #32016-12-13
Is construction at the site carried out strictly in accordance with the drawings? With such small tubes, the modifications on-site will likely be substantial; it is recommended to purchase a few extra ones, as the price should not be high.
Reply #42016-12-13
It depends on what type of pipe it is. For pipes with a DN20 diameter, seamless pipes, carbon steel pipes, and stainless steel pipes are all typically 6 meters long each; therefore, 48 meters would need to be purchased. If you want some extra length, just buy one that’s 54 meters long.
Reply #52016-12-13
Be a bit more flexible – 9 pieces of 6 meters each will do.
Reply #62016-12-13
It depends on the specifications and length; you need to compare for yourself to determine whether it’s more appropriate to go for options with a lower unit price in larger quantities, or to choose those with a higher unit price based on the actual length required. Seamless steel pipes are usually not available in custom lengths, and those in custom lengths come at a higher cost
Reply #72016-12-13
There are a few more thin pipes, and some areas have additional piping. Try to control the use of thick pipes. In practice, for example, stainless steel pipes are 6 meters long each; if 2 pipes of 10 meters are needed on site, the construction team will use a 6+4 arrangement rather than a 6+4,2+6+2 arrangement. In other words, there will be two 2-meter pieces left, and no 4-meter piece will remain.
Reply #82016-12-13
The actual purchase quantity is 1.03 times the amount specified in the drawings; this value can then be adjusted to reflect the full length of the pipe.
Reply #92016-12-14
A colleague said that it’s our side that needs to make the request
Reply #102016-12-14
It’s not strict; the skill level of the construction team is relatively low
Reply #112016-12-14
Understood, thank you very much. Is the DN50 one treated in a similar way?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.