Thread Content
Topic: Entrusted by the owner of a construction project, can a company that provides management services for the entire construction process (a management company under the agency model and possessing qualifications in supervision and project management) also undertake supervision tasks for that same project? Answering requirements and scoring criteria: 1. Requirements. Please hide your reply to this post; no scoring will be given in principle if it is not hidden. Hidden method: http://bbs.hcbbs.com/viewthread.php?tid=492556&page=1#pid2695620 v* ]; x1 W2 {: d1 Y 2 Rating. Each participant will receive a wealth reward of 3 to 5 points; if the responses are insightful and of sufficient depth, the score will be increased accordingly. "
According to the **project management regulations, supervision work can be carried out simultaneously.
This post was last edited by ms3210 on 2010-12-27 at 10:51; it’s necessary to have clarity; It’s easier to communicate when it’s family doing the work
According to Article 7 of Ministry of Construction Order No. 200, \"Provisional Measures for the Management of Construction Projects,\" a project management company may undertake supervision tasks for projects simultaneously, but it shall not engage in project contracting activities.
Within the same project, one cannot assume two roles at the same time, that is, being both the contractor and the supervisor.
Personally, I think it’s not okay. If management and supervision are combined, even if the supervision isn’t done properly, no one will know! I think it’s best for the project owner to set up a project department to manage the project, while hiring an external supervisor to oversee the construction site.
No, supervision must be carried out by the client or a third party appointed by the client.
This post was last edited and replied to by ms3210 on 2010-12-31 at 17:30. 1# ms3210: It shouldn’t be possible; otherwise, there would be no oversight.
This post was last edited by ms3210 on 2010-12-31 at 17:29. According to the new project construction regulations, this is not acceptable; a third party must carry out supervision. Otherwise, self-supervision and self-restraint are likely to result in quality issues.
This post was last edited by ms3210 on 2010-12-31 at 17:29. On December 15, 1995, the then Ministry of Construction and the then **Planning Commission issued a notice regarding the \"Regulations on Engineering Construction Supervision\", which came into effect on January 1, 1996. Article 20: Supervision agencies shall not contract out projects, nor shall they engage in the business of building materials, components, as well as construction machinery and equipment.