How many mm need to be cut off from the steel pipe or steel plate after flame cutting?

2021-08-14View Original

Thread Content

Experts: When using flame to cut steel pipes or steel plates, what distance in millimeters constitutes the heat-affected zone, and how many millimeters need to be removed? Which standard specifies this?
Reply #22021-08-14
Different materials have different requirements. For example, low-carbon steel only needs to have its oxide layer removed, but for high-alloy heat-resistant steel pipes, flame cutting is not recommended or allowed; gas cutting is required to remove the heat-affected zone
Reply #32021-08-14
Hello, expert. For low-carbon steel, it is only necessary to grind off the oxide layer – which standard specifies this requirement? Could you let me know?
Reply #42021-08-14
Check GB50235 and 50236; it’s there
Reply #52021-08-14
Yu always answers very clearly: lol

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.