HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

What are the pressure testing standards after purchasing valves and having them stored in the factory?

2025-06-22View Original

Thread Content

After purchasing valves and having them stored in the factory, how should pressure testing be carried out, and what are the standards for such testing? Is there any corresponding evidence?
Reply #22025-06-24
I. Core test items and standard requirements 1. **Shell strength test** – **Purpose**: To verify the structural integrity of pressure-bearing components such as the valve body and valve cover. - **Test parameters**: - Test pressure: 1.5 times the nominal pressure (PN) or the design pressure. - Medium: Clean water (for stainless steel valves, chloride ions must be controlled at ≤25ppm). - Holding time: ≥5 minutes (at room temperature), with no leakage or deformation. - **Applicable standards**: API 598, GB/T 13927, GB/T 26480 (equivalent to API 598). 2. **Sealing test** - **Classification and requirements**: - **Low-pressure sealing test**: The medium is gas (air/inert gas), with a pressure ≤ 0.6 MPa. - **High-pressure sealing test**: The medium is water or oil, at a pressure of 1.1 times PN. - **Leakage grade **: Classified as A to G according to ISO 5208 (soft seals require zero leakage, while metal seals allow a slight amount of leakage). - **Special tests**: – **Upper seal test**: For valves with an upper seal mechanism (such as gate valves and globe valves), the pressure is 1.1 times PN, and the packing gland must be loosened. 3. **Special condition testing** – **Fire resistance test**: Simulate a fire environment to verify the valve’s sealing performance at high temperatures. - Standards: API 607 (soft-sealed valves), API 6FA (line valves), JB/T 6899 (China). - **Low-temperature test**: Suitable for operating conditions below -40°C (such as LNG valves). - Standards: BS 6364, GB/T 24925; immersion testing in a liquid nitrogen environment is required. - **Micro-leak test**: Measures the amount of helium leakage; standard: ISO 15848 (certification for the leakiness of industrial valves). - **Life test**: Simulates opening and closing cycles (e.g., high-pressure valves are required to undergo ≥200 cycles per API 598); standards include JB/T 8858 (gate valves), JB/T 8863 (butterfly valves), etc. --- II. Relationship between test duration and size: The required holding time for valves of different sizes varies significantly, as follows: | Valve nominal size (DN) | Minimum time for shell testing | Minimum time for sealing testing | |-------------------|-----------------|-----------------| | ≤50 | 15 seconds | 15 seconds | | 65–150 | 60 seconds | 60 seconds | | 200–300 | 120 seconds | 60 seconds | | ≥350 | 300 seconds | 120 seconds | > *Note: Data compiled from GB/T 13927, API 598, and pipeline construction standards. * --- III. Additional requirements for special valves 1. **Nuclear-grade valves**: Must comply with RCC-M (France), ASME III (USA) or GB/T 19624 (China), with additional non-destructive testing and cyclic durability testing required. 2. **Control valve**: It is necessary to calibrate the travel positioning (4–20mA signal), flow coefficient (Cv/Kv values), and actuator dead zone. 3. **Large-diameter gate valves (DN≥600)**: They can be exempted from separate pressure testing and can be inspected simultaneously during system pressure testing. --- IV. Quality Control and Certification – **Mandatory inspection before shipment**: A pressure test record must be kept for each valve, including data on shell strength and sealing performance. - **Material verification**: The material must comply with ASTM standards (such as A216 WCB) or GB/T 12225 standards for copper alloys, with spectral analysis and hardness testing carried out as supplementary checks. - **International certifications**: CE (EU), SIL (Safety Integrity Level), API Mark certification. --- V. Recommendations for Standard Selection – **Petroleum/Chemical Projects**: API 598 and ASME B16.34 should be given priority. - **Domestic standard projects**: GB/T 26480 and GB/T 13927 are adopted. - **Special fields such as nuclear power/fire protection**: Additional industry-specific standards apply (such as GB 5135.6 for fire valves). > Key point: The valve must be thoroughly cleaned before testing; anti-seepage coatings are prohibited ; After the test, drain any remaining water and apply rust preventive oil, then close the inlet and outlet guards.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.