What should be done three days before a major maintenance overhaul of the equipment?

2018-11-22View Original

Thread Content

It has not undergone major maintenance; the unit has been sent for maintenance. What should be done in the first three days? Create access holes in large areas of tissue? Remove the valve?
Reply #22018-11-23
The manholes must be opened; it should be done in accordance with the maintenance plan, starting with those that have a longer maintenance cycle
Reply #32018-11-23
There’s no need to disassemble the valve; you need to prepare some information regarding the comprehensive inspection and distribute it to everyone, so that they know what needs to be checked during this inspection
Reply #42018-11-23
Strictly follow the major maintenance plan, taking things step by step; complete the work of each day on that same day, hold meetings every evening to conduct inspections, and arrange the tasks for the next day in accordance with the maintenance plan.
Reply #52018-11-24
Strictly follow the major maintenance plan, taking things step by step; complete the work of each day on that same day, hold meetings every evening to conduct inspections, and arrange the tasks for the next day in accordance with the maintenance plan.
Reply #62018-11-27
Take a good bath, get a good night’s sleep to recharge your energy, and go over everything in detail in bed; you’ll then know exactly what to do next.
Reply #72018-11-27
Ensure that the oil is completely removed; it must be totally cleared away~~~~~

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.