How to put the capacitor into operation after the transformer is operated in parallel

2017-01-12View Original

Thread Content

How to put the capacitors into operation after the transformers are operated in parallel? Currently, my two transformers are designed to operate in parallel, and neither transformer has separate capacitor compensation. When the two transformers are put into parallel operation, are both sets of capacitors automatically put into operation, or is one group put in automatically and one set of capacitors put in manually?
Reply #22017-01-12
Both sets of capacitors need to be invested, because according to what you said, each set of capacitors detects the line current from one transformer, excluding the current from the other transformer.
Reply #32017-01-18
You can put in two automatics, but be careful if it is a high-voltage capacitor.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.