【Daily Question】Utilities - Civil Engineering - 20190221

2019-02-21View Original

Thread Content

Delays in the project timeline caused by ( ) do not entitle to an extension of the deadline. A. The employer fails to provide the conditions necessary for commencement of work as stipulated in the contract. B. The employer fails to provide the advance payment for the project as agreed in the contract, resulting in the inability to carry out the work properly. C. Interruptions due to lack of water, electricity, or gas supply over a period of one week, not caused by the contractor, result in a total shutdown time of 6 hours. D. Force majeure. Answer: C

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.