【Daily Question】Hydropower Engineering - 20191204
Thread Content
Accelerate the development of the water metering system; metering facilities must be constructed concurrently with any new construction, renovation, or expansion projects; Existing structures that do not yet have metering facilities should be upgraded as soon as possible. In areas suffering from severe water shortages and those with over-extraction of groundwater, necessary facilities must be completed within a set timeframe. Measurement-based water supply has been fully implemented in all key projects of medium- and large-sized irrigation areas ; Small irrigation areas and the lowest-level canal systems have their measurement units refined according to management requirements ; For irrigation using groundwater, metering should be done at the well; where conditions permit, metering should be done per household. A. Automated water metering facilitiesB. IC cards for water meter inlets
C. Water meter inlets and below
D. Water meters
Answer: C