Participation reward: 2 Wealth. Correct reward: 9 wealth. According to the \"Code for Valuation of Construction Projects based on Bill of Quantities\" (GB50500-2013), for any item in the bill of quantities of a tendered project, if there is a variation in the quantity of work due to changes made by the owner, the principle for making adjustments is ( ). A. When the volume of work increases by more than 15%, the unit price for the increased portion should be reduced. B. When the volume of work decreases by more than 15%, the associated cost for measures should be increased. C. When the volume of work increases by more than 15%, the unit price for the increased portion should be increased. D. When the volume of work decreases by more than 10%, the associated cost for measures should be reduced. **: A
A. When the amount of work increases by more than 15%, the unit price for the increased portion of the work should be reduced
A. When the amount of work increases by more than 15%, the unit price for the increased portion of the work should be reduced
According to the \"Code for Quantitative Calculation of Construction Projects\" (GB50500-2013), for any item in the tendered bill of quantities, if there is a variation in the quantity of work due to changes ordered by the employer, the adjustment principle is ( A ). A. When the volume of work increases by more than 15%, the unit price for the increased portion should be reduced. B. When the volume of work decreases by more than 15%, the cost associated with those measures should be increased. C. When the volume of work increases by more than 15%, the unit price for the increased portion should be increased. D. When the volume of work decreases by more than 10%, the cost associated with those measures should be reduced