This post was last edited by hesonchang214 on 2017-5-27 21:44. Reward for participation: 2 Wealth. Correct reward: 6 wealth. Regarding the general contracting management model for construction, which of the following statements are correct? (  )   A. The subcontract must be signed between the general construction management unit and the subcontractor. B. The employer selects the subcontractor through bidding, without the need for the approval of the general construction management unit. C. The general construction management unit only charges a management fee and does not earn any profit from the difference between the overall contract price and the subcontract prices. D. Even if the general construction management unit refuses to approve a certain subcontract, it still remains responsible for managing that subcontracted work. E. The general construction management approach can significantly shorten the construction period. Answers: C, E
Reply #22017-05-27
Regarding the general contracting management model for construction, the correct statements are ( C ).   A. The subcontract must be signed between the general construction management unit and the subcontractor.  B. The employer selects the subcontractor through bidding, without the need for the approval of the general construction management unit.  C. The general construction management unit only charges a management fee and does not profit from the difference between the overall contract price and the subcontract prices.  D. Even if the general construction management unit refuses to approve a certain subcontract, it still remains responsible for managing that subcontracted work.  E. The general construction management approach can significantly shorten the construction period
Reply #32017-05-27
Regarding the general contracting management model for construction, the correct statements are (  CE ).   A. The subcontract must be signed between the general construction management unit and the subcontractor. B. The employer selects the subcontractor through bidding, without the need for the approval of the general construction management unit. C. The general construction management unit only charges a management fee for the overall project and does not profit from the difference between the total contract price and the subcontractor’s fees. D. Even if the general construction management unit refuses to approve a certain subcontract, it still remains responsible for managing that subcontracted work. E. The general construction management approach can significantly shorten the construction period

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.