Participation reward: 2 Wealth. Correct reward: 6 wealth. In the price adjustment formula, PD represents the amount due to the contractor for the work completed, as specified in the payment certificate; the costs that are not taken into account when determining this amount are ( ).   A. Price adjustment B. Withholding and payment of quality guarantee funds C. Adjusted contract price D. Agreed changes and other amounts E. Payment and recovery of advance payments Answer: A, B, D, E
Reply #22017-05-29
In the price adjustment formula, PD represents the amount for the work completed that the contractor is entitled to receive as per the agreed payment certificate; the costs that are not taken into account when determining this amount include (ABCDE).   A. Price adjustment   B. Withholding and payment of quality bond   C. Adjusted contract price   D. Agreed changes and other amounts   E. Payment and recovery of advance payments

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.