For temporary power supply in a newly built factory area, the cables need to run along the fence; do they also need to be buried or installed overhead? Are there any simpler alternatives?
Reply #22017-10-11
First, examine the overall layout plan of the factory site and draw a diagram showing the overhead path of the electrical wires. Second, if the factory area is not large, it is sufficient to run a cable along the perimeter wall; otherwise, it is better to place temporary transformers close to the load areas
Reply #32017-10-11
The main issue is that the power usage cycle is quite long, over a year. I’m worried that running it openly along the wall doesn’t comply with the standards. If it follows the specifications, can it only be buried or installed as an overhead line?
Reply #42017-10-11
It’s okay; temporary power lines aren’t monitored by anyone, so as long as proper protective measures are taken, they will eventually be removed.
Reply #52017-10-11
For a new factory facility, it is recommended to use an elevated installation; burying it can easily lead to conflicts with subsequent excavation work and create potential problems. If the project timeline is over a year, don’t hesitate to take the extra effort to ensure everything is done properly. When you’re done with the demolition and look back, you’ll realize that following the standards was the right thing to do. If the small details of a newly initiated project are not handled properly from the start, bad habits will develop over time, creating numerous problems in the work process. Remember
Reply #62017-10-11
Mount brackets on the wall to elevate them~~~ this prevents the cables from being damaged when they are on the ground during construction
Reply #72017-10-12
For temporary lines, if you don’t plan to recycle the cables, it’s best to bury them; if they are to be installed overhead, it is recommended to leave enough length headroom as per the layout plan.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.