Among the following options, those that belong to the technical measures for progress control in construction projects are (  ).   A. Prepare a resource requirement plan B. Conduct risk analysis of the project schedule C. Define the division of responsibilities for schedule control D. Select construction methods that are conducive to achieving the schedule goals Correct answer: D
Reply #22017-12-18
D. Select a construction plan that is conducive to achieving the schedule targets
Reply #32017-12-18
D. Select a construction plan that is conducive to achieving the schedule targets

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.