In the construction of thermal pipelines, for crossing projects, (  ) it is necessary to obtain the consent and cooperation of the pipeline operators responsible for the areas being crossed.   A. Pipes and their accessories B. Construction methods C. Construction planning D. Location of the work pit E. Sequence of project execution Correct answer: BDE
Reply #22018-01-09
In the construction of thermal pipelines, for crossing projects (BDE), it is necessary to obtain the consent and cooperation of the pipeline owners at the locations where the crossings take place.   A、Pipes and their accessories B、Construction methods C、Construction planning D、Location of the work pit E、Project execution procedure
Reply #32018-01-09
B、Construction method D、Location of the work pit E、Project execution procedure

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.