How is the impulse switching test for overhead lines carried out?

2018-06-29View Original

Thread Content

Regarding the requirement in 10.2.1 of GB50173-2014, which states \"4 – Perform three impulse closing operations on the unloaded line at the rated voltage\", how exactly should this commissioning test be carried out? Seeking advice
Reply #22018-06-30
Previously, the line was powered on three times using a formal working power supply voltage impulse; on the third attempt, all parts of the line operated normally and no further power outage was required, indicating that the impulse test was successful and the line could be put into operation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.