Identify Violations by Looking at Pictures (October 25, 2018, Issue 7 of October). Notes: 1. There are many violations at construction sites or production sites, which hinder stable and safe production; we hope everyone will point out the problems shown in the pictures to help them improve their work. Thank you for your participation and support! ! ! Photos of the scaffolding on site: Answers: 1. The footboards are not fully installed; 2. The height of the platform is inappropriate; 3. The footboards are not secured
Reply #22018-10-25
1. The scaffold lacks diagonal bracing; 2. The tray is not fully filled ; 3. The pedal is not secured ; 4. No safety net in place ; 5. The vertical pole is not perpendicular ; 6. The spacing between vertical poles is too large.
Reply #32018-10-25
1. Building codes for protective panels; 2. Unreasonable guardrails
Reply #42018-10-25
1. The scaffolding planks are not fully laid out; 2. There are no toeboards; 3. No inspection sign is available; 4. The planks of the middle level of the scaffolding are not properly overlapped
Reply #52018-10-25
1. The ramp is not fully covered; 2. The height is inappropriate, making construction difficult ; 3. Additional vertical poles should be added; it is not sufficient to rely solely on the pipe gallery for support. They can be erected separately from the ground, as long as proper support is ensured ; 4. No upper or lower passages ; 5. No construction fencing in place ; 6. No work instruction sign seen ;
Reply #62018-10-25
1. The scaffold lacks diagonal bracing; 2. The tray is not fully filled ; 3. The pedal is not secured ; 4. No safety net in place ; 5. The vertical pole is not perpendicular ; 6. Excessive spacing between vertical poles ; No construction fencing was installed ; No work instruction sign visible
Reply #72018-10-25
1. The scaffold was erected in violation of specifications, and the steps were substandard. 2. The height of the scaffold was inappropriate
Reply #82018-10-25
1. No safety net available. 2. The scaffolding is not built in accordance with standards, and the stepping boards are not fully laid out; 3 Additional vertical poles should be added; reliance solely on the pipe gallery supports is not sufficient, and they can be erected separately from the ground.
Reply #92018-10-25
The scaffold pads are not fully laid out; The distance between the horizontal bars and the vertical bars is large; there are no diagonal braces, no safety nets, and no safety warnings of any kind.....

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.