The primary power supply for Substation No. 10 of Guangxi Huayi Phase III project, which involves a production capacity of 320,000 tons per year of butyl octyl alcohol and acrylates, has been successfully established
Thread Content
At 11 a.m. on November 12, with the successful commissioning of the two 35kV main transformers, the primary power supply was successfully established at Substation No. 10 of Guangxi Huayi Phase III project, which involves the production of 320,000 tons per year of butyl acetate and acrylates. This marked the official activation of the project’s power supply system, providing a solid foundation for subsequent construction, installation, and testing activities. Project Name: Guangxi Hua Yi New Materials Co., Ltd.’s 320,000 tons per year butyl octanol and acrylate project (hereinafter referred to as the “Butyl Octanol and Acrylate Project”), and 20,000 tons per year polymerization inhibitor project (Phase I) (hereinafter referred to as the “Polymerization Inhibitor Project”).Project Owner: Guangxi Hua Yi New Materials Co., Ltd.
Location: The Butyl Octanol and Acrylate Project is located at Plot No. 27, east of Dolphin Road and south of Le Gou East Street, within the Qinzhou Petrochemical Industry Park, Qinzhou Port Economic and Technological Development Zone, Qinzhou City, Guangxi Zhuang Autonomous Region. Location of the antipollution agent production site: JinGu area of Qinzhou Petrochemical Industry Park, Qinzhou Port Economic and Technological Development Zone, Qinzhou City, Guangxi Zhuang Autonomous Region – to the west of Dolphin Road, to the east of Guangxi Hongyi New Materials Co., Ltd., to the south of LeGou East Street, and to the north of the northern zone of Guangxi Huayi New Materials Co., Ltd. Funding source: self-financing by the enterprise and bank loans. Project scale: Butanol and esters project: a facility capable of producing 160,000 tons per year of butanol and 160,000 tons per year of 2-ethylhexanol, along with a plant for producing 80,000 tons per year of 2-ethylhexyl acrylate. This includes supporting infrastructure such as intermediate storage tanks, product storage tanks, regional substations, cabinet rooms, cooling stations, incinerators, fire suppression ponds, and rainwater monitoring ponds. The total land area required is approximately 160 mu. The total investment is approximately 2 billion yuan. Polymerization inhibitor project: Construction will be carried out in two phases. In the first phase, a hydroquinone production facility with an annual capacity of 10,000 tons, along with associated facilities such as raw material and product storage areas, regional substation, and regional cabinet rooms, will be built ; The project involves a two-phase construction of a 4,000-ton/year phenothiazine production facility (accompanied by a 5,000-ton/year diphenylamine production facility), as well as supporting auxiliary facilities such as raw material and product storage areas; the total land area required is approximately 80 mu. The total investment for the first phase is approximately 400 million yuan.