Why is water filled to the brim in the equipment during the later stages of project construction?

2020-09-27View Original

Thread Content

Why is water filled to the brim in the equipment during the later stages of project construction? The reactor and pump have not been tuned yet. With the reactor filled with water, can it still be stirred by hand?
Reply #22020-09-27
Settlement inspection: During normal operation, the equipment is filled with a medium. Water of equal weight or more is used, based on the maximum amount of medium that may be present in the equipment under normal operating conditions, to check whether there is any settlement in the equipment’s foundation
Reply #32020-09-28
For atmospheric-pressure containers, seal tests and settlement tests are conducted
Reply #42020-10-07
Reactor vessels are all installed on floor steel frames, so settlement isn’t an issue
Reply #52020-10-12
Not a hydrostatic test? Isn’t it water intermodal transport? Then it could be a settlement test

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.