Why don’t cylinder-splitting devices with a diameter of 250 or less have a container certificate? It is said that the quality inspection agency does not oversee such devices with a diameter under 250, and they are not inspected upon leaving the factory.
You mean without a supervision and inspection certificate, right? Anything that meets clauses 1.3 and 1.5 of the Fixed Capacity Regulations should undergo supervision and inspection, and a supervision and inspection certificate should be issued
Steam distribution cylinder? There should be...
This post was last edited by Menghuan100 on 2017-2-20 at 21:12; according to the fixed capacity regulations, only those with an inner diameter of 150 or less are exempt from inspection. DN250 steam distributors that are less than 30 liters do not require inspection.
It’s impossible; that’s against the rules!
It has to be redone; the original welding work won’t meet the standards, so the blueprints need to be redesigned along with the calculation documents
Is the working pressure less than 0.1 MPa?
It may be a boiler accessory, and the design drawings require verification by a special inspection agency. A single inspection report is used for the production inspection; no separate inspection reports are issued for each cylinder. The warranty documents for the individual cylinders are included in the boiler’s warranty document.