For pressure vessels or atmospheric vessels that are welded on-site, does the contractor need to provide a complete set of documents, similar to those that come with the equipment supplied by the vessel manufacturer?
Reply #22017-03-22
A complete set of documents must be provided. In addition to all the documents required for manufacturing at the factory, pressure vessels assembled on-site also need to come with documents related to equipment installation.
Reply #32017-03-22
Thank you for the reply. Are there any standard requirements for providing it?
Reply #42017-03-28
If it is a pressure vessel, relevant documents must be provided. You belong to the on-site team; according to Chapter 6 of the Major Pressure Vessels Regulations, pressure vessels welded on-site by this team require supervised inspection. (6.1.2.1). So it’s definitely not possible to conduct inspections without any information on the original components. For specific requirements, refer to those specified in the major capacity regulations.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.