Design pressure and operating pressure of the equipment

2017-06-17View Original

Thread Content

What do the design pressure and nominal operating pressure of a device actually mean? Can the actual operating pressure exceed the device’s nominal operating pressure for an extended period of time (as long as it does not exceed the design pressure)?
Reply #22017-06-17
The design pressure is generally higher than the operating pressure; it is used to determine the dimensions of the equipment as well as the selection of pipes, flanges, and fittings, and it is taken into consideration during the design process. The actual pressure must not exceed the operating pressure for an extended period of time
Reply #32017-06-17
This post was last edited by Menghan100 on 2017-6-17 at 11:02. Design pressure is generally higher than operating pressure and is used for strength calculations. The actual pressure must not exceed the operating pressure for an extended period of time.
Reply #42017-06-19
At the same operating temperature, it is possible to operate for an extended period at pressures not exceeding the design pressure; however, this will cause regulatory authorities to give you trouble: lol
Reply #52017-06-19
The design pressure should not differ much from the nominal operating pressure...
Reply #62017-06-19
Operating the pressure above the parameters specified on the equipment’s nameplate is considered improper operation, although it does not pose any safety risks. If it is necessary to operate at pressures above the rated pressure over a long period of time (as long as this is within the set pressure range of the safety valve), it is possible to request modifications to the pressure vessel, adjust the operating parameters, and carry out the relevant procedures in accordance with Section 5 of the Pressure Vessels Regulations, along with submitting the necessary approvals

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.