Contents of the quality assurance materials for the pressure-bearing components of pressure vessels

2017-08-08View Original

Thread Content

We have recently started working on quality assurance. Due to an aging workforce, we want to establish a standard procedure for the contents of the quality assurance documents related to the pressure-bearing components of pressure vessels. A few points have been listed; I hope the experts in this area will discuss them. I: The certificates required for the tube sheet are as follows: 1. Quality certificate for pressure-bearing components (forgings); 2. Quality certificate for the base material of the forgings; 3. Heat treatment inspection report for the forgings; 4. Mechanical property test report; 5. Ultrasonic testing report for the forgings; 6. Re-inspection report for raw materials.

II: For the reduced-diameter sections (eccentric or conical shapes), the following certificates are required: 1. Quality certificate for pressure-bearing components; 2. Quality certificate for the base material; 3. Re-inspection report for raw materials; 4. Non-destructive testing report; 5. Certificate of material quality and warranty for welding materials; 6. Inspection certificate.

III: The certificates required for the end caps are as follows: 1. Product qualification certificate; 2. Component data report; 3. Quality certificate for the material; 4. Physical and chemical analysis report; 5. Heat treatment report; 6. Inspection certificate. End caps with seams also require a certificate of welding material quality and a non-destructive testing report.

IV: The certificates required for manholes are as follows: 1. Product qualification certificate for manholes; 2. Inspection report on the appearance and geometric dimensions of the product; 3. Quality certificate for the base material; 4. Product qualification certificate for the forgings; 5. Physical and chemical analysis report for the forgings; 6. Certificate of material quality and warranty for welding materials; 7. Inspection certificate for the manhole segments.

V: The certificates required for flanges are as follows: 1. Product qualification certificate for forgings; 2. Quality certificate for the base material; 3. Physical and chemical analysis report; 4. Refer to item 1 for forgings.

VI: The certificates required for steel (tubes, plates) are as follows: 1. Warranty certificate for steel, tubes, and plates (with a QR code or barcode); 2. Official stamp from the manufacturer (supplier) along with the signature or seal of the responsible person.

VII: The certificates required for welding materials are as follows: 1. Warranty certificate for welding materials; 2. Official stamp from the welding material manufacturer (supplier) along with the signature or seal of the responsible person.

Note: All of the above-mentioned certificates must bear the official stamp of the manufacturing unit. Please advise!
Reply #22017-08-10
Well organized, thank you! I’ve learned it.*
Reply #32017-08-11
The last edit to this post was made by niat8888 on 2017-8-11 at 12:36.
I: The certificates required for the tube sheet are as follows:
1. Quality certificate for pressure-bearing components (forgings)
2. Quality certificate for the base material of the forgings
3. Heat treatment inspection report for the forgings
4. Mechanical property test report (retest report when required)
5. Ultrasonic testing report for the forgings
6. Retest report for raw materials (when required)

II: The certificates required for the reduced-diameter sections (eccentric, conical shapes) are as follows:
1. Quality certificate for pressure-bearing components
2. Quality certificate for the base material
3. Retest report for raw materials (when required)
4. Non-destructive testing report
5. Material certificate and quality guarantee sheet for welding materials (one copy only)
6. Inspection certificate (required for covers that are part of the structure)

III: The certificates required for covers are as follows:
1. Product qualification certificate
2. Component data report
3. Quality certificate for the material
4. Physical and chemical analysis reports
5. Heat treatment report
6. Inspection certificate (required only for covers with seams; welding material certificate and non-destructive testing report are also required)

IV: The certificates required for manholes are as follows:
1. Product qualification certificate for manholes
2. Inspection report on the appearance and geometric dimensions of the product
3. Quality certificate for the base material
4. Product qualification certificate for the forgings used in manholes
5. Physical and chemical analysis reports for the forgings
6. Material certificate and quality guarantee sheet for welding materials
7. Inspection certificate for the manhole sections (? ) V: The certificates required for flanges are as follows: 1. Certificate of conformity for forged products; 2. Quality certificate for the base material; 3. Physical and chemical testing reports. For forged products, refer to item 1. VI: The certificates required for steel (tubes, plates) are as follows: 1. Warranty certificate for the steel, tubes, or plates (with a QR code or barcode); 2. Seal from the manufacturer (supplier) along with the signature or stamp of the responsible person. VII: The certificates required for welding materials are as follows: 1. Warranty certificate for the welding materials; 2. Seal from the welding material manufacturer (supplier) along with the signature or stamp of the responsible person. Note: All of the above-mentioned certificates must bear the seal of the manufacturing unit. As for the physical and chemical testing reports, it is not strictly necessary to provide them; they are only needed for reference
Reply #42017-08-11
For the manhole, an inspection certificate should be obtained for the entire unit.
Reply #52017-08-13
Very good. Thank you, moderator. It is recommended to present it in a tabular format for easier comparison and clarity. It really is confusing right now.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.