Is the first routine inspection of the boiler conducted one year after installation is completed, or one year after the installation is approved?

2018-02-27View Original

Thread Content

RT, the regulations are rather vague
Reply #22018-02-27
Aren’t special equipment devices only used after passing the inspection first?
Reply #32018-02-28
Registration can only be carried out after installation acceptance is completed and an inspection report is issued; the installation acceptance must take place with the boiler operating at full load. The regulations state that registration must be done before use or within one month after use
Reply #42018-02-28
Register after the installation has passed the acceptance inspection
Reply #52018-02-28
On my end, it’s based on the acceptance report
Reply #62018-02-28
On my end, it’s based on the acceptance report
Reply #72018-03-08
Generally, we follow the date stated on the boiler registration certificate. Generally, this time will be a bit later than the completion time of installation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.