Issues with the production efficiency of pressure vessels?

2019-02-16View Original

Thread Content

The company currently has too many contracts related to boilers and autoclaves, which makes it impossible to carry out all the work. I would like to ask all of you experts for your advice on how to improve production efficiency, so that our company can enhance its productivity and enable us to earn higher salaries – or at least still receive some salary
Reply #22019-02-16
One of the key factors affecting the project timeline is material procurement. In particular, for certain outsourced components such as forged flanges and exterior heads, ordering should not be delayed until the drawings are available; purchases should be made as soon as the drawings are finalized, so that production progress is not hindered by shortages of materials.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.