Dear sea friends: I’ve been in this industry for only a short time, so I have a question. For the hydraulic testing of containers, if a M20 threaded hole is drilled in a DN200 blind flange to install a pressure gauge, is it necessary to conduct any calibration? Is it checked based on the opening in the flat cover? Thank you all!
Reply #22019-06-12
There is no need for verification to meet the minimum wall thickness requirement for openings as specified in GB150
Reply #32019-06-15
There is no need for verification to meet the minimum wall thickness requirement for openings as specified in GB150
Reply #42019-06-22
For openings in flat covers, it is recommended to carry out reinforcement calculations in accordance with Article 6.3.4 of GB150.3. The allowable minimum opening size without additional reinforcement generally applies to housings with fittings.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.