What is the risk of using air pressure for testing equipment and pipelines in engineering project construction?

2019-11-24View Original

Thread Content

In the construction of engineering projects, what are the risks associated with using air pressure for testing equipment and pipelines? Where exactly do the dangers of air pressure testing lie? Is there a mandatory limit of 0.6 MPa?
Reply #22019-11-24
For details, see TSG D0001-2009.
Reply #32019-11-24
Which clause of TSG D0001-2009 specifies the mandatory limit of 0.6MPa?
Reply #42019-11-24
There are no restrictions. According to GB20801, it is still necessary to refer to the design specifications and the pipeline data sheet (a list of pipeline characteristics) to determine the hazard level of the medium, in order to decide whether gas pressure testing is required. Generally, gas pressure testing can be carried out during the system pressure test before starting up the equipment. For details, see gb/t20801.5-2006
Reply #52019-11-24
The specifications take into account the risks associated with pressure testing and the requirements for such testing.
Reply #62019-11-24
There is one in 50235, but it doesn’t seem to be mandatory; a value above 0.6 MPa carries a relatively high risk.
Reply #72019-11-24
The owner has agreed, or relevant provisions allow for a pressure test at above 0.6 MPa.
Reply #82019-11-24
Due to the high compression ratio of gases and the significant pressure changes associated with temperature variations, the hydraulic energy storage capacity for the same volume is much lower than that of gases. In the event of a pipeline leak or rupture, this can cause considerable damage; therefore, hydraulic testing should be used as much as possible
Reply #92019-11-25
If a hydraulic test is possible, pneumatic testing is generally not used. If a hydraulic test is possible, a pneumatic test can be carried out as well; generally, a hydraulic test should be done first, and only after it is successful should a pneumatic test be conducted

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.