Overlapped heat exchanger pressing

2020-10-15View Original

Thread Content

The shell side is connected, while the tube side is not – how should pressure testing be carried out on the shell side? See the figure for parameters
Reply #22020-10-15
GB/T151 8.13.8 specifies that pressure testing also needs to be carried out in the overlapping condition; at present, it is not clear how to perform pressure testing in this overlapping state
Reply #32020-10-15
GB/T151 8.13.8 specifies that pressure testing also needs to be carried out in the overlapping condition; at present, it is not clear how to perform pressure testing in this overlapping state
Reply #42020-10-15
Option 1: My own idea – connect the shell sides together and apply a pressure of 0.975 MPa (which, according to calculations, should be sufficient); however, the verification shows that this pressure is too high for the heat exchanger below. Option 2: According to the verification recommendations, apply pressures of 0.975 MPa/0.85 MPa to each shell side separately, and then apply a combined pressure of 0.125 MPa
Reply #52020-10-16
First conduct pressure tests separately, then assemble them and conduct a pressure test together; it’s just a bit more complicated.
Reply #62020-10-16
Use a precision pressure gauge as required by the design; if you’re not sure, it’s also okay to apply pressure separately first and then assemble them together to apply pressure. If the tube side and shell side of some heat exchangers are not properly welded or sealed, it is very difficult to apply pressure to them. It needs to be disassembled and reassembled many times.
Reply #72020-10-20
Proceed in accordance with the requirements on page 109 of 151: after separate pressure testing of the tube side and shell side and confirmation that these tests are successful, carry out overlapping assembly; for the shell side, use a pressure of 0.125
Reply #82020-10-20
Yes, for the above two heat exchangers, pressure testing is carried out on their shell sides and tube sides respectively; once they pass the testing, the two heat exchangers are assembled together and subjected to a combined pressure test at 0.13 MPa.
Reply #92020-10-21
Fight separately; why fight together? The heat exchanger below is just a basic component. Next, consider the purpose of water pressure: if all the components that are subject to pressure have been checked, what’s the point? GB151 applies to Unicom’s heat exchangers.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.