Construction process for chemical plant projects

2022-01-05View Original

Thread Content

1. Feasibility study. (Performed by the enterprise or an entrusted intermediary service agency) 2. Site selection for the project. (Enterprises go to the planning or construction authorities to obtain a project site selection approval letter and a construction land planning permit). 3. Project approval or registration. (Submitted by the enterprise to the NDRC for project approval or registration) 4. Conduct an environmental impact assessment. 5. Approval for environmental impact assessment (carried out by a qualified intermediary service agency commissioned by the enterprise). (The environmental protection department approves the environmental impact report) 6. Prepare reports on safety pre-assessment and occupational disease hazard pre-assessment. (Enterprises entrust qualified intermediary service agencies) 7. Review of the safety pre-assessment report. (Expert review) 8. Decision on the approval of the pre-assessment report for occupational disease hazards. (Health department) 9. Filing of the safety pre-assessment report. (Enterprise registration with the safety supervision department) 10. Safety review. (Safety supervision department conducts a safety review) 11. **Approved. (After passing the safety review, the safety supervision department issues an approval letter.) 12. Apply for a business license. (The enterprise shall go to the industrial and commercial authorities to obtain a business license with the approval document.) 13. Obtain a land use certificate. (Handled by the enterprise at the land administration department) 14. Conduct preliminary design. (Commissioned by the enterprise to a qualified design unit) 15. Preliminary design review. (Reviewed by the fire department, health department, and safety supervision department) 16. Construction drawing design. (Entrusted by the enterprise to a qualified design firm) 17. Apply for a construction project planning permit. (Enterprise applies for a construction project planning permit) 18. Apply for a construction permit. (Enterprises apply to the construction department for a construction permit) 19. Fire safety inspection. (After the completion of a construction project, the fire department conducts an inspection for completion approval.) 20. Obtain a permit for the use of special equipment. (Handled by the enterprise at the quality supervision department) 21. Trial production. (Environmental protection department’s approval for the trial production period) 22. Completion acceptance. (The health department, environmental protection department, and work safety supervision department conduct inspections.) 23. Apply for a work safety license. (Applied for by hazardous chemicals manufacturing enterprises to the provincial safety supervision department). 24. Apply for a production license for industrial products. (Enterprises apply to the provincial market supervision authorities for the products listed in the catalog issued by the **State Administration for Market Regulation**).
Reply #22022-01-05
It explains it perfectly, but it’s not that easy to put into practice
Reply #32022-01-06
This post was last edited by sgh1966 on 2022-1-6 at 10:21 to add some supplementary details: Basic process for chemical plant construction 1. Feasibility study. (To be carried out by the enterprise or an entrusted intermediary service agency) 2. Site selection for the project. (Enterprises apply to the planning or construction departments for a project site selection opinion and a permit for urban construction land use.) 3. Project approval or filing. (Submitted by the enterprise to the Development and Reform Commission or the Economic and Information Technology Commission for project approval or registration) 4. Environmental impact assessment (1) Groundwater assessment. (Entrusted by the enterprise to a qualified intermediary service agency) (2) Prepare an environmental impact assessment report. (Entrusted by the enterprise to a qualified intermediary service agency) (3) Conduct a review of the environmental impact assessment report. (Expert review, led by environmental protection authorities) (4) Obtain approval for the environmental impact assessment report. (Handled by the enterprise with the environmental protection authorities) 5. Safety pre-assessment (1) Prepare a safety pre-assessment report. (Entrusted by the enterprise to a qualified intermediary service agency for) (2) Review of the safety pre-assessment report. (Expert review, led by the safety supervision department) (3) Obtain approval for the safety pre-assessment. (Handled by the enterprise at the safety supervision department) (4) Filing of the safety pre-assessment report. (Enterprise registration with the work safety supervision department) 6. Preliminary assessment of occupational disease hazards (1) Prepare a preliminary assessment report on occupational disease hazards. (Entrusted by the enterprise to a qualified intermediary service agency) (2) Review of the pre-evaluation report on occupational disease hazards. (Expert review, led by the health department) (3) Obtain the approval decision for the pre-assessment of occupational disease hazards. (To be submitted by the enterprise to the health department) 7. Special section on safety facility design. 8. Review of safety facility design (conducted by a qualified design firm commissioned by the enterprise). (Promoted by the safety supervision department) 9. Approval of the design review for safety facilities. (After the safety facility design review is approved, the safety supervision department issues an approval letter.) 10. Special section on fire protection design. 11. Fire protection design review and approval (carried out by a qualified design firm commissioned by the enterprise). (After the fire protection design is approved, the emergency management department issues an approval letter.) 12. Apply for a business license. (The enterprise shall go to the industrial and commercial administration department to obtain a business license with the approval document.) 13. Water resources assessment: (1) Prepare a report on water resources assessment. (Entrusted by the enterprise to a qualified intermediary service agency) (2) Conduct a review of the water resources assessment report. (Expert review, led by water resources management authorities) (3) Obtain approval for the water resources demonstration report. (Handled by the enterprise at the water resources management department) (4) Obtain a water withdrawal permit. (Handled by the enterprise at the water resources management department) 14. Soil and water conservation plan (1) Prepare a soil and water conservation plan. (Entrusted by the enterprise to a qualified intermediary service agency) (2) Conduct a review of the soil and water conservation plan. (Expert review, with participation from soil and water conservation authorities) (3) Obtain approval for the soil and water conservation plan. (Enterprises shall handle this with the soil and water conservation administration department) 15. Energy conservation assessment (1) Prepare an energy conservation assessment report. (Entrusted by the enterprise to a qualified intermediary service agency) (2) Conduct a review of the energy conservation assessment report. (Expert review, led by the National Development and Reform Commission or the Economic and Information Technology Commission) (3) Obtain approval for the energy conservation assessment report. (Handled by the enterprise at the Development and Reform Commission or the Economic and Information Technology Commission) 16. Prevention and control of geological disasters: (1) Prepare a report on the prevention and control of geological disasters. (Conducted by the enterprise or a commissioned intermediary service agency) (2) Evaluate the geological disaster prevention and control report. (Expert review, led by the land and resources management department) (3) Obtain approval for the geological disaster prevention report. (Enterprises go to the land and resources administration department to handle this.) 17. Conduct preliminary design. 18. Construction drawing design (carried out by a qualified design firm commissioned by the enterprise). 19. Lightning protection design review (carried out by a qualified design firm commissioned by the enterprise). (Handled by the enterprise at the meteorological department) 20. Prepare the detailed design for construction. (Commissioned by the enterprise to a qualified design firm) 21. Review of the development detailed plan. (Expert review, organized by planning or construction departments) 22. Approval of the detailed construction plan. (Handled by the enterprise at the land and resources administration department) 23. Fire protection design. 24. Fire protection design review (carried out by a qualified design firm commissioned by the enterprise). (Organized by the emergency management department) 25. Apply for a construction project planning permit. (Handled by the enterprise at the planning and construction department) 26. Apply for a construction land use planning permit. (Handled by the enterprise at the planning and construction department) 27. Apply for a construction project permit. (Handled by the enterprise at the planning and construction department) 28. Obtain a land use certificate. (Handled by the enterprise at the land and resources administration department) 29. Apply for a registration certificate for the use of special equipment. (If any, the enterprise shall go to the technical supervision department to handle it) 30. Trial production. (Environmental protection agency approves the trial production period) 31. Completion acceptance (1) – Health department ; (2) —— Health department ; (3) —— Environmental protection department ; (4) —— Environmental protection department ; (5) —— Work safety supervision department ; (6) —— Emergency management department ; (7) —— National Development and Reform Commission or Ministry of Economy and Information Technology ; (8) —— Meteorological department ; (9) —— Planning and construction department. 32: The enterprise shall handle it at the land and resources administration department. 33: Involves chemical manufacturing enterprises applying to the provincial safety supervision authorities. 34: Enterprises apply to the provincial market supervision authorities for the products listed in the catalog issued by the **State Administration for Market Regulation.
Reply #42022-01-07
The old requirement lacks one important element
Reply #52022-01-20
I’ve learned something; thank you! Thanks♪(・ω・)ノ
Reply #62022-05-14
Very detailed, thanks for sharing :)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.