Thread Content
Successful first-time commissioning of the propylene compressor turbine in the purification unit of the Baofeng methanol project by Sinochem Sixth Construction Company Author/Source: Sinochem Sixth Construction Company Date: 2020-03-16 Clicks: 241 At 17:16 on March 14, the propylene compressor turbine in the purification unit of the Baofeng methanol project, operated by the Third Installation Company under Sinochem Engineering Sixth Construction Company, completed its overspeed trip test, marking the successful first-time commissioning of this turbine. At 13:00 on the 14th, the operator pressed the start button, and the turbine began its trial operation. All operations were carried out smoothly, and various parameters such as shaft vibration, shaft displacement, and temperature (oil temperature, shaft temperature) showed normal values with excellent data, meeting the design requirements. Before the turbine testing, the Baofeng Purification Project Team assigned technical personnel to form a testing team, developed a testing plan, and conducted repeated inspections of systems such as lubricating oil, cooling water, and instrument air prior to the testing. They also provided safety and technical risk briefings to the workers, implemented each item of the testing plan, and confirmed that all conditions for testing were met, thereby ensuring the smooth progress of the turbine testing process.