Thread Content

When restarting the reformation process, is there a sequence between starting the recycle hydrogen compressor and putting into use the waste heat recovery large drum as well as the water circulation system? Or the advantages and disadvantages of different commissioning sequences. Discussion is welcome!
Reply #22021-05-13
It doesn’t matter which one is done first; the important thing is to complete both steps before turning on the heating
Reply #32021-05-13
1. Direct hydrogen to the outlet of the hydrogen circulation pump, then start the pump. 2. Turn on the furnace to raise its temperature. 3. First start the forced circulation water pump; as the temperature in the furnace rises, then start the boiler feed water pump, adding water intermittently
Reply #42021-05-13
First, rinse with water to clean it and maintain a certain water level, then establish circulation and start the furnace; these two steps can also be carried out simultaneously.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.