The issue of steam pipe thrust

2022-05-04View Original

Thread Content

May I ask: Is it sufficient to install only fixed supports at the thrust points of the steam piping network shown in the diagram? Or do both the fixed support and the compensator need to be installed?
Reply #22022-05-04
Why not use a rotary compensator?
Reply #32022-05-04
Why not use a rotary compensator?
Reply #42022-05-05
The drawing only shows the fixing brackets; it does not indicate whether compensators are needed, so it’s not entirely clear!
Reply #52022-05-07
In general, fixed supports are used in areas where there is high pipeline thrust; therefore, unless specified in the drawings, a fixed support is used here as well
Reply #62022-05-07
Whether a fixing frame is required should be specified in the construction drawings; the construction party has no right to decide this.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.