60% scale model review for the hydrogen tank area and methanol finished product tank area of the Tianying Integrated Hydrogen, Storage, Ammonia, and Alcohol Production (Phase I of chemical manufacturing) project in Anda City
Thread Content
A 2.5 billion yuan investment! Review of the Project to Produce Green Methanol from Carbon Dioxide 2025-12-15 19:55 · Coco Stinky Uncle in the Countryside Recently, the review of 60% scale models of the hydrogen tank area and the methanol finished product tank area for Anda City’s Tianying Wind, Solar, Hydrogen Storage, Ammonia, and Methanol Integration (Phase I of the chemical production facility) project was successfully completed. This review focused on the core tank farm units of the project. The participants used 3D models to conduct a comprehensive evaluation of the hydrogen tank farm and the methanol finished product tank farm from professional perspectives such as the scientific nature of the process flow and equipment layout, design safety redundancy, feasibility of construction, convenience of operation and maintenance, and rationality of inspection and repair procedures. The owner’s project team provided optimization suggestions regarding key aspects such as equipment spacing, pipeline routing, and operating space, offering valuable insights for the subsequent refinement of the design. In response to the suggestions and comments raised during the review process, the design team promptly addressed them on the spot, demonstrating its efficient problem-solving capabilities and a commitment to excellence in design quality. After the meeting, the project owner stated that the professional competence and dedication demonstrated by the Tianchen team have laid a solid foundation for the high-quality progress of the project. The successful completion of this 60% model review not only marks an important milestone in the project’s design phase, but also provides guidance for further design development through comprehensive analysis by various parties. On July 9, the full text of the environmental impact assessment report for the Tianying Integrated Hydrogen, Ammonia, and Alcohol Production (Phase I of the chemical project) in Anda City was made public. Anda Tianying New Energy Co., Ltd. is a wholly-owned subsidiary of China Tianying, established in October 2023. It plans to invest in and construct the Anda Tianying Integrated Wind, Solar, Energy Storage, Hydrogen, Ammonia, and Methanol Project (Phase I of the chemical industry) within the Fine Chemicals Industrial Park in the Anda Economic Development Zone, Heilongjiang Province. This project is part of the “integrated wind, solar, energy storage, hydrogen, ammonia, and methanol” series of projects; specifically, it pertains to the production of green hydrogen and green methanol. The total investment in this project amounts to 2.5 billion yuan. Its main components include methanol production facilities, hydrogen production units, and related utility and auxiliary engineering works. This project utilizes the simultaneously constructed \"Anda City Tianying Integrated Wind, Solar, Hydrogen Storage, Ammonia, and Alcohol Production Project (utilization of biomass waste heat and electricity as well as green carbon production)\” to capture and recover carbon dioxide from flue gas, which is then used together with hydrogen produced on-site to synthesize green methanol. Once completed, the project will be capable of producing 100,000 tons of green methanol per year. Project Name: Anda Tianying Integrated Wind, Solar, Hydrogen Storage, Ammonia and Methanol Project (Phase I of Chemical Industry)Construction Unit: Anda Tianying New Energy Co., Ltd.
Industry Categories: C2614 Manufacture of organic chemical raw materials (methanol synthesis); C2619 Manufacture of other basic chemical raw materials (hydrogen production via electrolysis)
Project Nature: New construction
Location: North Area of the Fine Chemicals Industrial Park, Anda Economic Development Zone, Heilongjiang Province
Total Investment: The total investment for the project is 2.5 billion yuan, of which 110.776 million yuan is allocated to environmental protection efforts, accounting for 4.4% of the total investment.
Land Area: Approximately 555.4 mu, or 370,267 m²
Number of Employees: The project requires a workforce of 240 people.
Working Hours: Production operates on a four-shift, three-rotation system, running 24 hours a day. There are 333 operating days per year, resulting in an annual production time of 8,000 hours. The equivalent operating time for the methanol synthesis unit is 4,724 hours, while that for the electrolyzers is 3,940 hours.
Construction Period: 24 months