The acceptance of a chemical engineering technology transfer contract requires 72 hours of continuous and stable operation, but is full capacity absolutely necessary?

2017-10-20View Original

Thread Content

The acceptance of a chemical engineering technology transfer contract requires 72 hours of continuous and stable operation, but is full capacity absolutely necessary?
Reply #22017-10-20
It’s necessary, definitely – and it has to operate at the design load limit
Reply #32017-10-20
How can it be determined whether the performance indicators promised in the TTC contract are met when operating at sub-optimal capacity?
Reply #42017-10-20
Acceptance is based on whether the desired production levels and efficiency are achieved; therefore, production should still be carried out according to the load specified in the contract.
Reply #52017-10-20
It is definitely necessary to operate at full capacity in order to determine whether the design capacity, quality, safety, and other requirements are met.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.