2017-11-01View Original

Thread Content

This post was last edited by hesonchang214 on 2017-11-8 09:39. Fill in the blanks: After the installation of the indoor fire hydrant system, test the fire hydrants located at ( ) on the roof level or in the water tank room, and test the fire hydrants at ( ) on the ground floor; if they meet the design requirements, then it is considered successful. Answer: One Two
Reply #22017-11-01
After the installation of the indoor fire hydrant system, test hydrants on the roof level (or in the water tank room) and (two) hydrants on the ground floor should be used to conduct test discharges; compliance with the design requirements constitutes acceptance.
Reply #32017-11-01
After the installation of the indoor fire hydrant system is completed, one test fire hydrant should be selected from the roof level or the water tank room, and two fire hydrants from the ground floor to conduct test discharges; the system is considered satisfactory if it meets the design requirements.
Reply #42017-11-01
After the installation of the indoor fire hydrant system is completed, one test fire hydrant should be selected from the roof level or the water tank room, and two fire hydrants from the ground floor to conduct test discharges; the system is considered satisfactory if it meets the design requirements.
Reply #52017-11-01
After the installation of the indoor fire hydrant system is completed, one test fire hydrant should be selected from the roof level or the water tank room, and two fire hydrants from the ground floor to conduct test discharges; the system is considered satisfactory if it meets the design requirements.
Reply #62017-11-01
One location in the roof or water tank room, and two locations on the first floor. Could you please let me know whether it’s a fill-in-the-blank question or a true/false question? It seems quite difficult to figure out
Reply #72017-11-01
After the installation of the indoor fire hydrant system is completed, one test fire hydrant should be selected from the roof level or the water tank room, and two fire hydrants from the ground floor to conduct test discharges; the system is considered satisfactory if it meets the design requirements.
Reply #82017-11-01
After the installation of the indoor fire hydrant system is completed, one test fire hydrant should be selected from the roof level or the water tank room, and two fire hydrants from the ground floor to conduct test discharges; the system is considered qualified if it meets the design requirements.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.