I just became a technician recently. What documents are needed during the construction process?
Reply #22018-07-13
Secondary modification of the device: no drawings available, high-pressure pipelines
Reply #32018-07-13
Oh, I’ve encountered that before; but back then we were operating at low pressure. Are you just changing the pipelines? Can the device location be changed? If there are no drawings available, one can draw simple diagrams manually; draw a diagram for each pipeline that is to be modified. The original drawings and the revised versions can be provided, along with notes indicating the pipe diameter, temperature, pressure, medium, and material used. After compiling this information, a procurement plan can be prepared, along with a maintenance plan and a schedule for carrying out the repairs. The construction team should sign off on this and provide a guarantee ; It’s necessary to carry out the preparatory work before construction. For the construction phase, we had the construction team establish the standards for installation, which were then verified by the supervision engineer. Finally, tasks such as flaw detection, pressure testing, purging, and airtightness checks were carried out, and the relevant documents were kept. If necessary, the thickness was measured, and the original records were archived. This is based on my personal experience; you should adapt it to your own situation. I hope this can help you
Reply #42018-07-13
It is recommended to engage a qualified design firm for the design work, and a qualified construction company for the construction and supervision
Reply #52018-07-14
The device doesn’t have original drawings; initially, the design institute was in charge of on-site supervision, but later the construction company refused to pay, and the design institute stopped providing the drawings. The existing pipes were not inspected for defects nor pressure-tested. It’s quite awkward now; I don’t have any information at all
Reply #62018-07-15
Well, according to the current techniques, one can simply draw it by hand; using an Excel spreadsheet will suffice. It’s even better if one knows how to use CAD. After drawing it, any necessary modifications can be made. Once completed, testing such as flaw detection and pressure testing should be carried out, and the relevant documents should be properly stored

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.