In the PID, should the flanges, threads, and whether a short pipe is needed be indicated?

2019-04-22View Original

Thread Content

This post was last edited by 2005180005 on 2019-4-22 at 17:50. In PID diagrams for process engineering, should flanges, threads, and whether short pipes are needed be shown? Otherwise, how can those specializing in piping (3D) tell which parts are flanges and which ones are threads?
Reply #22019-04-22
I need short tubes; nothing else, unless there are special requirements
Reply #32019-04-22
In PID for the process engineering field, should flanges, threads, and whether short pipes are needed be illustrated? Otherwise, how can those specializing in piping (3D) tell which parts are flanges and which ones are threads? How do I draw it? Each pipeline has a corresponding material grade table, which defines the types of connections for the pipelines. The number of flanges and elbows is determined by the pipeline layout, and it cannot be shown. Flanges for connecting equipment, valves, instruments, etc., should be drawn.
Reply #42019-04-22
The images have been uploaded; see the top – they show the representation methods in PID for threaded and flanged connections respectively
Reply #52019-04-22
For short pipes, flanges are required; threads are not needed. There are specialized professionals who create piping diagrams
Reply #62019-04-22
List the standard specifications; for special requirements, draw them out
Reply #72019-04-23
The first time I saw it, the safety valve had threads. For plug welding, what is the drawing method? It seems to be a drawing method used in axonometric diagrams.
Reply #82019-04-23
For socket welding, nothing is drawn to represent it
Reply #92019-04-23
For socket welding, nothing is drawn to represent it
Reply #102019-04-23
Well, I’m not familiar with this area, thanks!
Reply #112019-04-23
As for PID, the short sections of the pipe are generally not drawn separately, unless the material of the pipe differs... An interface separation is required. As for bolts and such, the corresponding bolt length and quantity will be determined based on the pipe diameter and weight rating used

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.