2019-08-08View Original

Thread Content

When planning the equipment layout for a fine chemical production workshop, the client requested that lifting holes be installed on the workshop floor. However, I wonder if placing them in the middle of the floor might not be safe Is it necessary to install it against a wall? I found some guidelines regarding equipment layout, but there are no clear instructions on how to arrange things like platforms. So, based on everyone’s experience, where is it generally reasonable to locate the lifting points used to lift materials during the production process?
Reply #22019-08-08
Place it where it is most needed for lifting; whether it is secure or not still depends on safety facilities.
Reply #32019-08-08
It is recommended that when locating the lifting opening, consideration should be given to facilitating the transportation and loading/unloading of equipment; it should be placed on one side so as not to affect the operation of other equipment, and this area can also be used for maintenance purposes. Regarding the safety concerns you’re worried about, it’s sufficient to install a protective fence at least 1.5 meters high around the lifting area. Oh, and it’s best not to have any pipes laid underground at the lifting opening. Prevent damage from heavy pressure. For reference.
Reply #42019-08-09
Well, this lifting opening is mainly used to lift materials onto the feeding platform for feeding purposes; therefore, I left plenty of space on the sides. Considering various factors, I thought placing the lifting opening in the middle could save some labor. However, I’m worried that having it in the middle might not be safe. If protective barriers can be installed, it should help ensure safety, and then there shouldn’t be any problems
Reply #52019-08-16
The chemical engineering design manual states that, when the plant is short due to the equipment located on the floors, the lifting hole should be placed at the end near the gable wall; if the length of the plant exceeds 36 meters, the lifting hole should be located in the center of the plant. The lifting holes should not be made too large; generally, they are kept at 2.7 meters. For larger equipment, installation walls or installation doors are required.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.