Is water commissioning required before the initial operation of a gas fractionation unit? What consequences will arise if the water in the system’s memory cannot be completely drained after water interconnection?
It is not necessary to carry out purging or explosive purging
If water interconnection is not carried out, how can it be ensured that instruments, pumps, and other equipment are in good condition and functional?
How did you become a front-line technician? Water-conveyance systems can be used for joint commissioning, employee training, technical practice, and learning about DCS applications; they can also be used for further purging. It is possible to further observe the usage of towers, containers, heat exchange equipment, pipes, instruments, valves, and pumps, providing an opportunity for corrective actions. By exposing various issues before commencement and resolving them, better conditions can be created for starting work. The so-called clean construction is just a gimmick with no real meaning. It contains water; at the beginning of operation, monitor the liquid level in the dehydration package of the tower top reflux tank closely, and be prepared for dehydration.
Try not to do it! Otherwise, it will take a long time for the products to meet the quality standards!
It is best to avoid water transport; if it must be done, it is preferable not to introduce water into the tower. Otherwise, the floating valves on the tray plates are likely to get clogged, which affects the tower’s separation efficiency and results in product quality that does not meet standards
The tray floating valves are prone to clogging, and it is difficult to achieve satisfactory product quality