Old K says every week – talking about things in the petrochemical design industry. Post 24: Category codes for design documents

2020-11-27View Original

Thread Content

Old K says every week – Talks about things in the petrochemical design industry, Post 24: Regulations on design document category codes. Design document category codes are established to facilitate the numbering and modification of such documents. Some design institutes include the design document category code in the design document number, while others do not. Some design institutes use two-digit numbers to denote the categories of their design documents, while others use English abbreviations; currently, more institutes use English abbreviations. The category codes for design documents in some design institutes consist of a main category code plus a sub-category code; the main category code is an English abbreviation, while the sub-category code is two digits. The English abbreviations for common design document categories are shown in the table below: Table 24-1 English Abbreviations for Common Design Document Categories. Sequence Number, Document Category, English Name of Document Category, Abbreviation. 1, Document List, DLT; 2, Index, IDX; 3, Description, DES; 4, Calculation, CAL; 5, Data Sheet, DSH; 6, Specification, SPE; 7, Drawing, DWG; 8, List (equipment list, piping list, etc.), LST; 9, Material Take Off, MTO; 10, Shop Drawing, SDW; 11, Risk Assessment Report, RAR; 12, Design Basis, DBA; 13, Design Information, DIN; 14, Design Information Transmittal, DIT; 15, Design Modification Notice, DMN; 16, Process Flow Diagram, PFD; 17, Piping & Instrument Diagram, PID; 18, Utility Flow Diagram, UFD; 19, Utility Piping & Instrument Diagram, UID; 20, Utility Distribution Diagram, UDD; 21, Requisition, REQ; 22, Inquiry, INQ; 23, Technical Bid Evaluation, TBE; 24, Requisition for Purchase Order, POR; 25, Isometric, ISO; 26, Material Standard Specification, MSS; 27, Bar Bending Schedule, BBS; 28, Bill of Material, BOM; 29, Schematic Diagram/Diagram, DIG; 30, Standard Drawings, SDG; 31, Sketch, SKT; 32, Manual, MNL; 33, Vendor Document Information VDI; 34, Vendor Document Review, VDR; 35, Shop Inspection Requirements, SIR; 36, Inspection and Test Plan, ITP; 37, Letter of Conformity, LOC.

In each week, I’ll talk about various aspects of the petrochemical design industry. For previous posts, please see the links below: Post 1 – The Development History of China’s Survey and Design Industry: https://bbs.hcbbs.com/thread-3031149-1-1.html; Post 2 – Management in the Survey and Design Industry: https://bbs.hcbbs.com/thread-3036417-1-1.html; Post 3 – The Development of Drawing Technologies in Design Institutes: https://bbs.hcbbs.com/thread-3039960-1-1.html; Post 4 – The Evolution of Specialization in Petrochemical Design Institutes: https://bbs.hcbbs.com/thread-3045261-1-1.html; Post 5 – The Organizational Structure of Petrochemical Engineering Companies: https://bbs.hcbbs.com/thread-3050591-1-1.html; Post 6 – Contract Management in Design Management: https://bbs.hcbbs.com/thread-3054762-1-1.html; Post 7 – Management of Design Basis Data in Design Management: https://bbs.hcbbs.com/thread-3058184-1-1.html; Post 8 – Quality Management in Design Management: https://bbs.hcbbs.com/thread-3061718-1-1.html; Post 9 – Schedule Management in Design Management: https://bbs.hcbbs.com/thread-3062161-1-1.html; Post 10 – Management of Design Documents in Design Management: https://bbs.hcbbs.com/thread-3069580-1-1.html; Post 11 – Meeting Management in Design Management: https://bbs.hcbbs.com/thread-3073327-1-1.html; Post 12 – Management of Bonus Distribution in Design Management: https://bbs.hcbbs.com/thread-3077492-1-1.html; Post 13 – The Construction Process in Petrochemical Projects: https://bbs.hcbbs.com/thread-3082708-1-1.html; Post 14 – Content and Procedures of Process Professional Design Illustrated: https://bbs.hcbbs.com/thread-3086849-1-1.html; Post 15 – Explanation of PID Versions and PID Modification Management: https://bbs.hcbbs.com/thread-3091076-1-1.html; Post 16 – Common Energy-Inefficient Designs in the Petrochemical Industry: https://bbs.hcbbs.com/thread-3095859-1-1.html; Post 17 – Project Work Breakdown: https://bbs.hcbbs.com/thread-3100837-1-1.html; Post 18 – Issues Related to Design Talent Training: https://bbs.hcbbs.com/thread-3105529-1-1.html; Post 19 – An Overview of Pump NPSH in a Few Words: https://bbs.hcbbs.com/thread-3109916-1-1.html; Post 20 – On Excessive Patent Applications: https://bbs.hcbbs.com/thread-3111855-1-1.html; Post 21 – Pressure Drop and Energy Consumption of Control Valves: https://bbs.hcbbs.com/thread-3116754-1-1.html; Post 22 – Names and Abbreviations of Project Design Phases: https://bbs.hcbbs.com/thread-3121148-1-1.html; Post 23 – Abbreviations for Design Specialties: https://bbs.hcbbs.com/thread-3123778-1-1.html
Reply #22020-11-27
Acronyms used in a project are generally determined in accordance with international conventions as well as the practices of various engineering companies; there are differences between companies from the UK and the US on the one hand, and those from South Korea and Japan on the other. A list of project acronyms is usually issued after the first project coordination meeting, and it is updated from time to time thereafter.
Reply #32020-11-30
Very practical, thumbs up! ! ! Thank you! ! !

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.