Experts: What procedures need to be carried out throughout the process from the construction to the commissioning of a chemical project? Which departments should be approached to handle this?
Feasibility study report, environmental impact assessment, design and survey work, design; after the environmental impact assessment is approved, the procedures for construction are carried out, and upon completion of construction an inspection is organized. A commissioning plan, operating procedures, and reports are prepared, a pollution discharge permit is applied for, and then commissioning begins
There’s plenty to check out on the HaiChuan forum; it has everything you need to learn*.
Procedures for project construction: https://bbs.hcbbs.com/thread-538509-1-1.html. I’m a newcomer seeking help; I have taken on a newly established chemical engineering project and am in urgent need of information regarding the procedures for carrying out such project construction. Thank you very much! https://bbs.hcbbs.com/thread-1534192-1-1.html What further procedures are required after the project is completed in order to start operations? https://bbs.hcbbs.com/thread-1105504-1-1.html What procedures are required during the trial production of a new construction project? https://bbs.hcbbs.com/thread-691716-1-1.html
If everything is done strictly in accordance with the procedures, the process will take too long. Building before approval is, in theory, illegal, and there is also a risk that the structure will not meet the requirements and thus need to be modified or demolished. If there’s enough time, follow the process; if not, spend some money to ask the evaluation agency for some advice. Both environmental impact assessments and safety assessments require review by expert panels; qualified assessment agencies are familiar with these experts, and investing enough money can improve efficiency and reduce complications