Is it necessary to pressurize the instrument along with the connection part of the pipeline during pipeline pressure testing?

2017-09-02View Original

Thread Content

For the newly installed water pipes, does the pressure inlet and the metal base at the installation temperature need to be opened first, and should they be pressurized along with the pipes?
Reply #22017-09-02
It is necessary; pressure testing is required for everything in front of the valve
Reply #32017-09-03
It’s necessary; otherwise, after drilling, who can guarantee that the new opening won’t have any problems?
Reply #42017-09-03
Follow the pipeline diagram; that’s where the boundary between pipelines and instruments lies. In other words, the pipe socket and the mating flange or threaded connection must be subjected to water pressure.
Reply #52017-09-03
Fight together during the suppression phase to ensure everything meets the standards

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.