Sulfuric acid pipeline flow meter, with static discharge bonding terminals provided; the meter has two wires that are not connected to anything

2018-03-29View Original

Thread Content

May I ask, is there any problem with the status shown in the image? If so, how should it be corrected?
Reply #22018-03-29
Generally, there is one grounded terminal; if the device has two terminals, they may be the working terminal and the protection terminal, with the latter needing to be connected to the protection ground at the installation site
Reply #32018-03-29
If there are multiple electrodes or a grounding ring, only protective grounding is required
Reply #42018-03-30
The ground wire can be fixed to the static bypass ear
Reply #52018-03-30
Connect the two black wires of the flow meter to the grounding rings welded on the pipes on either side, and that’s it. This keeps it at the same potential as the work area and safely. No potential difference means no interference.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.