2019-10-16View Original

Thread Content

Experts, please help me figure out whether to attack For that specification, it’s also possible to go straight to that secondary valve
Reply #22019-10-17
Personally, I think the direct connection option is better – it’s easier to install and provides better waste removal.
Reply #32019-10-17
I think it’s fine; our leader said it’s okay? Add it there
Reply #42019-10-18
For general flow transmitters, it is best to use a five-valve or three-valve assembly; if such an assembly is not available, it is recommended that the secondary valve be placed as close as possible to the transmitter. By the way, the balance valve is missing in the diagram.
Reply #52019-10-18
I didn’t draw it; there’s a balance valve on site. What is the secondary valve? It’s better to add it at the Naga section, or it’s more reasonable to add it along the sewage line

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.