Who usually handles the automated systems SAT FAT SIT? Is a third party needed?

2020-03-07View Original

Thread Content

Who usually carries out tasks such as the Site Acceptance Test SAT, the Factory Acceptance Test FAT, and the Site Integration Test SIT for automated systems? Is a third party needed?
Reply #22020-03-08
1. FAT, 2. SAT, 3. SIT – Factory acceptance is generally carried out between the supplier and the buyer; It is carried out among the SAT and SIT suppliers and buyers, with the cooperation of the construction unit; the supervisor may also be invited to participate and sign.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.