I would like to ask how to arrange the 36-hour large cycle for coking in a 2×55-hole top-mounted coke oven
Reply #22017-04-01
Determine your push sequence, 5-2, 9-2, and then schedule furnace 110 for 36 hours: lol
Reply #32017-04-02
It’s a 5--2 sequence. Should the scheduling cycle table take working hours into account? Should maintenance tasks be scheduled during working hours?
Reply #42017-04-06
There is no need to consider working hours; only in this way can the coking time in each carbonization chamber be kept the same. If working hours are forced to be staggered, the coking times will vary.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.