Issues related to gas purification for 3 million tons of coking capacity

2018-11-07View Original

Thread Content

As the title suggests, how long does it generally take, at the shortest, to go from pile driving to operation for a gas purification plant associated with a 3-million-ton coking facility? Those with experience, please share their insights
Reply #22018-11-13
This question is still a bit vague. As you said, once pile driving starts and everything goes smoothly at each stage, it should take about a year.
Reply #32018-11-15
It’s probably 10 to 12 months, depending on how well you manage the project timeline
Reply #42018-11-20
The minimum is not less than ten months; it should be around a year.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.