A total investment of 2.052 billion yuan! The 250,000-ton coal tar processing project in Panzhihua has entered the commissioning phase and is set to go into operation soon

2026-02-04View Original

Thread Content

“After 13 months of intensive construction, it has entered the joint commissioning phase and will be put into operation soon! ”On January 16, within the Gliping Chemical Industry Park in the West District of Panzhihua City, the main structure of the first phase of the 250,000 tons per year coal tar deep processing project was completed. Various pipelines stretched across the factory area, while workers moved among the numerous installations, carrying out installation and testing tasks in an organized manner. The main construction works for the office building, various production workshops, and tank areas have been completed, and final commissioning work is currently in progress. This key project, with a total investment of over 2 billion yuan and an area of 300 mu, is controlled by Ansteel Chemical Technology Co., Ltd. It is implemented in three phases. It is a \"core project\" carefully introduced by Panzhihua to promote the transformation and upgrading of the coal chemical industry; it embodies the local community’s hopes for a shift from traditional coal chemical production to more sophisticated and high-end forms of production. This project will help extend the coal coking industry chain and provide strong impetus for strengthening the regional coal chemical industry chain. Moving toward higher quality and greener practices to drive the transformation and upgrading of traditional coal chemical industries. Entering the production area of the first phase of the project, one can see raw material storage tanks, distillation towers, heating furnaces, etc., all standing tall. The numerous pipelines function like industrial \"veins\", connecting various production units together to form a cohesive whole. Here, coal tar undergoes a magnificent \"transformation\"; through various stages of processing, it is converted from a raw material into a range of high-quality chemical products such as asphalt, anthracene oil, and washed oil, thus becoming chemical raw materials with high added value that are widely used in fields such as advanced manufacturing. Behind the seemingly complex pipeline layout lies the key to the project’s green transformation in the coal chemical industry. In January 2025, the Provincial Development and Reform Commission’s review comments on the project’s energy efficiency report indicated that the project’s energy efficiency level was at an advanced level for the industry. “From raw material feeding to product discharge, the entire process takes place within pipes. ”Liu Jianyong, director of Sichuan Lvxinding Carbon Industry Co., Ltd., said that the production technology has been upgraded through iterative improvements, moving steadily toward higher standards and greater sustainability. Taking continuous vacuum distillation, the main production process, as an example, the use of pipes of different colors together with systems such as waste heat recovery enables a significant reduction in gas consumption; the heat from asphalt and distillates is fully utilized, resulting in almost no visible emissions from the exhaust gases. The double-furnace double-tower process used in the industrial naphthalene distillation unit incorporates \"green technology\"; the two distillation towers work in harmony with the heating furnace, which not only results in a simple and easy-to-control process but also significantly increases the yield of naphthalene. By separating naphthalene from phenol oil and methylnaphthalene oil, this approach further enhances the purity of the product. As planned, the project will in the future expand into high-value areas such as benzene hydrogenation and needle coke. Once all phases of the project are completed, a full-chain system of \"basic chemicals – fine chemicals – high-end new materials\" will be established. Providing excellent frontline support and ensuring coverage throughout the entire project lifecycle: it took only 13 months from the start of construction to the commissioning phase. Faced with various challenges such as a tight schedule, heavy workload, complex geological conditions, and construction during the rainy season, the efficient progress of the project was made possible by comprehensive support and assistance. To advance the construction of major projects, Panzhihua has established a new mechanism based on the principle of \"city-level leaders taking charge directly + industry-leading departments handling key aspects + departments responsible for recruitment and support coordinating efforts + counties (districts) and parks bearing primary responsibility for implementation + state-owned enterprises providing cooperation + departments in charge of approval processes offering services.\" For each major project, a \"service specialist\" is assigned to provide comprehensive support throughout the entire process, from negotiations and contract signing to operation and achievement of desired results, ensuring oversight throughout the project lifecycle. Huang Jiajie is the “service specialist” for this project. When talking about the project, he was very knowledgeable; we offer agencies and assistance services for enterprises, proactively addressing various issues such as land use, energy requirements, and approvals that arise during project construction, thereby ensuring its smooth progress. A responsible official from the management committee of the Gliping Park in the West District of Panzhihua City explained that the park’s government service center offers over 200 services related to businesses, enabling them to handle various affairs without leaving the park. In terms of infrastructure, the park has also established supporting facilities such as a special services fire station, a hazardous materials parking lot, and an intelligent monitoring and control platform. Dual water sources and dual power supplies ensure the smooth construction and operation of the project. For Panzhihua, the completion and operation of this project are of great significance; it will not only enable the efficient utilization of the abundant coal tar resources in the Panxi region but also serve as a strong model that can drive development and strengthen the regional coal chemical industry chain. As the leader of the new generation of coal chemical industry chains, this project is continuously generating a strong agglomeration effect. “Since the project was launched, we have carried out more than 20 targeted investment promotion efforts focused on the industrial chain, aiming to attract additional enterprises from upstream and downstream sectors and thus achieve the transformation and upgrading of the coal chemical industry. Relevant projects have been successfully contracted, and the benzene hydrogenation supporting project has been included in the investment plan. ”A relevant official from the park management committee stated that going forward, relevant resources will be fully utilized, with an optimal business environment and strong support for various elements serving as the foundation to ensure that related projects can proceed efficiently, with signing leading to immediate implementation, commencement of work right after signing, and production starting as soon as work begins. Every effort will be made to develop a new generation of coal chemical industry clusters, thereby injecting strong momentum into the high-quality development of the park. 250,000 tons/year tar processing project: With a total investment of 2.052 billion yuan and covering an area of 300 mu, it will be constructed in three phases to build a production line capable of processing 250,000 tons of coal tar per year. One phase of this investment amounts to 452 million yuan, which is used to build production lines with an annual capacity of 128,000 tons of asphalt, 68,000 tons of anthracene oil, and 21,000 tons of raffinate, along with the necessary supporting facilities ; Phase 2 plans to build a 150,000-ton benzene hydrogenation production line ; Phase three focuses on the high-value-added product segment, aiming to build a 80,000-ton needle coke production line. Once the project is fully completed, it is expected to create more than 370 new job opportunities.
Reply #22026-02-04
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 3001 to 2025, the Beijing Aerospace Power Research Institute developed China’s first polyolefin crushing and feeding machine, which has now been put into operation. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5712691 (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #32026-02-05
【Haichuan Spring Festival Teahouse】Old items seen when returning to one’s hometown – do you recognize them? (26)-- https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5713053 (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))
Reply #42026-02-05
[Common Issues in Haichuan Pipeline Design] – A compilation post; images and text are being updated. Feel free to join the discussion: https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5705828 (Source: Haichuan Chemical Forum (Hua Haichuan Liu hcbbs))
Reply #52026-02-06
【Ten Years of Rapid Development in Chemical Engineering Equipment】CGN’s 8.6-meter molten salt tank-type collectors from 2030 to 2025: breakthroughs in large-aperture, high-concentration molten salt heating systems https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5712784 (Source: Haichuan Chemical Engineering Forum (HCBBS))
Reply #62026-02-07
【Ten Years of Rapid Development in Chemical Equipment】The world’s first industrial demonstration plant for high-pressure methane-carbon dioxide dry reforming was successfully put into operation from 2030 to 2026. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5712818 (Source: Haichuan Chemical Forum (HCBBS))
Reply #72026-02-08
【Ten Years of Rapid Development in Chemical Equipment】The first of its kind within the refining and chemical processing sector, Zhongli Company’s 1 million tons per year delayed coking unit waste gas treatment project was successfully completed and accepted in terms of mechanical requirements. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5713019 (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))
Reply #82026-02-08
【Haichuan Spring Festival Teahouse】Old items seen when returning to one’s hometown – do you recognize them? (16)--Warm memories of winter in the south https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5712746 (Source: Haichuan Chemical Industry Forum (Hua Hai Chuan Liu hcbbs))
Reply #92026-02-09
【HaiChuan Equipment Guessing Game】An irregular-shaped octopus? https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5713178 (Source: HaiChuan Chemical Forum (HuaHaiChuanLiu hcbbs))
Reply #102026-02-09
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2030 to 2026, Zhongke Fuhai’s large-scale low-temperature refrigeration systems will contribute to accelerating the development of the **IP-SAFE project for scientific and educational infrastructure**. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5713024 (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #112026-02-09
【Haichuan Spring Festival Tea House】Old items seen upon returning to one’s hometown – do you recognize them? (41) Looking forward to a bountiful harvest in autumn https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5713402 (Source: Haichuan Chemical Industry Forum (Hua Hai Chuan Liu hcbbs))

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.