Progress of Qinghai Damei’s 1.8 million tons/year methanol-to-olefins project

2019-01-01View Original

Thread Content

On September 30, the physical construction of the 110kV substation and plant external wiring project was completed. On November 3, the physical construction of the air compressor station for the nitrogen production air separation unit was completed. On November 30, the construction projects for the tank farm, the plant-wide comprehensive warehouse, and the gas elimination and prevention center were completed. On December 22, the regional substation was handed over. On December 26, the polypropylene unit and the coal unloading and storage unit were physically handed over. On December 28, the physical construction of the polyethylene plant was completed. On December 29, the physical facility for the methanol-to-olefins complex was handed over.
Reply #22019-01-01
This post was last edited by Zhizhi Ming on 2019-1-1 at 22:17. With so many projects being carried out simultaneously towards the end of the year, it seems that the political implications outweigh the actual progress of these projects. In such a snowy and icy environment, can the production staff carry out system purging and pressure testing?
Reply #32019-01-02
CCCC can make the payment now; plenty of money is available. Hello everyone, Happy New Year.
Reply #42019-01-02
I agree with you; delaying the completion of the work causes the greatest harm to the construction companies, and it is also a great disrespect toward the hard work of the construction workers! Happy New Year!
Reply #52019-01-02
First, please look at the fourth floor. Second, construction isn’t underway at the moment; even when the flowers bloom in spring next year, trials cannot be carried out in a timely manner
Reply #62019-01-02
The entities involved in transportation…… Chinese culture is actually profound and extensive
Reply #72019-01-02
The period before the New Year is a peak time for theft. It once happened that after CCCC signed the agreement and the responsibility for supervision was transferred, it was discovered during the joint tests after the holiday that many precious metal parts had been stolen. The emergency purchase came at a high cost, yet the delivery of the car was still delayed.
Reply #82019-01-02
It depends on whether it’s properly secured; it has nothing to do with whether it’s done by CCCC or not. The owner failed to carry out the necessary work after CCCC finished its task
Reply #92019-01-02
Difference between \"Entity Completion\" and \"Substantial Completion\": Definitions of completion for international and domestic projects https://bbs.hcbbs.com/thread-538815-1-1.html (Source: Haichuan Chemical Industry Forum)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.